Insights · Data Center Policy

HIT-30 and Data Centers: What Türkiye's HIT-Data Center Call Means for Investors

A USD 1.5 billion support budget, demanding technical thresholds and incentives that narrow as targets are met. Here is what the call asks of a project, what it offers, and why delivery capability decides the outcome.

Press Bulletin / 7 min readBy SERBAN
USD 1.5bnTotal support budget of the HIT-Data Center call
30 MW+Minimum IT capacity per data center
≥ 50%Of capacity compatible with AI hardware
PUE ≤ 1.4Maximum Power Usage Effectiveness

Artificial intelligence and cloud computing have put data centers at the heart of Türkiye's industrial policy. Through the HIT-30 High Technology Investment Program, the Ministry of Industry and Technology runs a dedicated HIT-Data Center call with a total support budget of USD 1.5 billion. The call targets large-scale, AI-ready facilities that meet demanding technical thresholds. For investors, hyperscalers and colocation operators, it is a significant opportunity, but capturing its value depends as much on engineering and delivery as on the application itself.

01Why are data centers a HIT-30 priority?

According to the official program website, HIT-30 plans about USD 30 billion of support for high-tech investments by 2030, across more than 30 priority investment subjects in 8 areas. President Erdoğan launched the program in Istanbul on 26 July 2024, and hyperscale data centers were named at the launch among the calls planned to follow the program's first six calls. "Cloud Services Provided by Large-Scale Data Centers" is listed as a priority investment subject under Digital Technologies.

The official call text explains why: advances in artificial intelligence, big data, high-performance computing and cloud services have made scalable, high-capacity, technologically advanced data centers a strategic necessity. The call addresses three needs: high-capacity, secure data centers; hardware and infrastructure for AI workloads; and an ecosystem that prevents idle capacity in IT hardware. Its goal is to meet Türkiye's short-term data infrastructure needs while building long-term capacity for AI and future digital technologies.

Ministerial statements set a national goal of raising data center capacity from about 250 MW to 1 GW by 2030. The Türkiye Artificial Intelligence Action Plan 2026–2030, announced by President Erdoğan in June 2026, also targets at least 1 GW of installed data center capacity by 2030, together with at least USD 10 billion of mostly private investment in data centers, cloud and AI. Both targets come from official statements reported in the press rather than from the HIT-30 program website.

Aerial view of a large data center campus under construction with rooftop cooling units and a generator yard
Hyperscale capacity is built as a campus: data halls, cooling plant, generator yard and grid connection have to be planned and delivered together.

02What does the HIT-Data Center call require?

Minister of Industry and Technology Mehmet Fatih Kacır announced the HIT-Data Center call (HIT-Veri Merkezi) in October 2025, together with the HIT-AI, HIT-Quantum and HIT-Industrial Robot calls. As of November 2026, the official calls page lists it among the active calls. The official call materials set out four qualifying criteria:

Scale30 MW+ IT capacity

Each data center must offer at least 30 MW of IT capacity.

AI readiness≥ 50% AI-compatible

At least half of the capacity must be compatible with AI hardware.

EfficiencyPUE ≤ 1.4

A maximum Power Usage Effectiveness of 1.4.

IntegrationCloud & AI services

Investments integrated with large-scale cloud or AI service centers.

According to the program FAQ, a project that does not meet every criterion may still receive partial support, at a level the Ministry considers appropriate. Investors whose plans center on AI compute should also review the companion HIT-AI call, which is currently active as well. It has a USD 1.6 billion budget and targets large-scale cloud investments that include AI services and at least USD 100 million of AI investment.

03Which incentives are available?

The data center call lists three supports:

Up to 50%Tax support
Up to 10%Energy support, of the investment
PlusEmployment supports

These sit within a broader program-level toolbox that can include reduced corporate tax, customs duty and VAT exemptions, social security premium support, qualified personnel support, and interest or profit-share support, as well as land allocation, financing instruments, and market development tools such as a public procurement guarantee. The program states that total support across all categories can reach up to 100% of the fixed investment amount.

None of this is a fixed package. HIT-30 is implemented under Türkiye's project-based incentive scheme, including Law No. 6745 on Supporting Investments on a Project Basis and Decision No. 9903 on State Aids in Investments, together with related decrees and communiqués. Which instruments apply, and at what rates, is decided project by project. Investors should confirm eligibility and terms with the HIT-30 Program Office and with their own legal and financial advisers.

04What should investors have ready before applying?

The process is straightforward on paper, but each requirement is demanding:

  1. Minimum scale

    HIT-30 projects require a minimum fixed investment of TRY 2 billion.

  2. Application

    The investor emails a project presentation to the HIT-30 Program Office, which begins evaluating it no later than 15 business days after receipt.

  3. Approval path

    Projects the Program Office finds suitable are submitted for Ministry approval and then to the Presidency for a Presidential Decree. After the decree is issued, the company applies for its incentive certificate through E-TUYS, the Ministry's online incentive management system.

  4. Investor profile

    Applicants are expected to have a strong financial structure and relevant experience. Strategic partnerships with stakeholders that have international experience strengthen an application.

Timing matters. There is no fixed application deadline, but intake for a call closes once its targeted number of projects and capacity is reached, and the incentives on offer become less generous as targets are met. The program aims for investments to be completed by 2030, although final completion may extend beyond 2030 if a project reaches a specified stage by then. Special incentive packages end between 2030 and 2032, depending on the subject. Projects that reach technical maturity early are best placed.

Data center electrical room with a long line-up of switchgear on one side and UPS cabinets on the other
AI-ready capacity starts in the electrical room: power distribution and redundancy have to be sized for high-density racks from the first drawings.

05Why does execution capability decide the outcome?

An incentive certificate does not build a data center. The call's thresholds are engineering commitments as much as eligibility criteria:

High-density power

Making at least half of a 30 MW+ facility compatible with AI hardware means planning for rack densities well above those of conventional enterprise or colocation halls. Power distribution, redundancy and structural loads must be designed for this from the first drawings.

Advanced cooling

Holding PUE at or below 1.4 while hosting high-density AI workloads calls for efficient cooling strategies, such as free cooling, containment and, increasingly, liquid or hybrid cooling readiness. It also calls for highly efficient mechanical, electrical and plumbing (MEP) systems.

Reliability

The call does not set a Tier level, but facilities that serve large-scale cloud or AI service centers are expected to run continuously in practice. Tier III-level design and rigorous commissioning are the usual way to deliver that.

Speed to market

Intake closes as targets are reached, and incentive windows end between 2030 and 2032. Delays in design, procurement or construction therefore carry a real financial cost.

Data center chiller plant room with blue and green chilled-water pipework, pumps on concrete plinths and water-cooled chillers
The PUE ceiling of 1.4 is set in the plant room as much as in the data hall.
When design, construction, MEP and commissioning are split across many parties, each handover adds risk to cost, schedule and the efficiency figures the project has committed to.

Integrated delivery reduces that risk.

Commissioning engineer in a hard hat and high-visibility vest testing cabling at an open rack with a handheld meter
Commissioning and integrated systems testing turn a finished building into a facility that performs as designed.

06How can SERBAN support investors pursuing large-scale data center projects?

SERBAN is an EPC+ data center construction company founded in 2014 and a member of Açık Holding. It has delivered Tier III data centers with a combined IT load of more than 100 MW and 22,150 m² of white space. The company's scope covers design, engineering, construction, MEP, and Level 1–5 commissioning and integrated systems testing (IST), including PUE optimization and liquid-cooling readiness for AI-ready facilities.

For investors preparing projects under programs like HIT-30, SERBAN can help turn targets such as a PUE of 1.4 or lower, high-density AI-ready capacity and Tier III reliability into a commissioned facility, with a single party accountable from design through commissioning.

SERBAN is not affiliated with the HIT-30 program and plays no role in its evaluation; applications and incentive decisions remain solely between investors and the Ministry of Industry and Technology.

Key takeaways

  • HIT-30 plans about USD 30 billion of support for high-tech investment by 2030, and large-scale data centers are a priority subject.
  • The HIT-Data Center call has a USD 1.5 billion total support budget and is listed as active as of November 2026.
  • Qualifying projects need at least 30 MW of IT capacity, at least 50% AI-hardware-compatible capacity, a PUE of no more than 1.4, and integration with large-scale cloud or AI service centers.
  • Listed supports include tax support of up to 50%, energy support of up to 10% of the investment, and employment supports. All support is determined project by project.
  • There is no fixed deadline, but intake closes once targets are reached, and incentive packages end between 2030 and 2032. Applications in HIT-30 priority areas can also be submitted without an active call.

Planning a high-capacity, AI-ready data center?

Talk to SERBAN about design, construction and commissioning under one accountable team.

Official call details and application guidance are available on the HIT-30 program website.

Sources
  • HIT-30 program website (hit30.sanayi.gov.tr): home page, calls, sectors, incentives and FAQ pages, including the HIT-Data Center and HIT-AI call summaries. Checked 19 November 2026; call status re-checked on 26 November 2026.
  • CNN Türk, 17 October 2025: Minister Kacır's announcement of the new calls and the 250 MW to 1 GW capacity target.
  • Ekonomi Gazetesi, 13 June 2026: Türkiye Artificial Intelligence Action Plan 2026–2030.
  • TGRT Haber, 26 July 2024: launch of the HIT-30 program.
  • serban.com.tr/data-center: SERBAN company figures.
  • Photographs are illustrative and do not show a specific facility or SERBAN project.