References

Project Name Location
Red Haven (Edgnex by Damac & Vodafone Investment) İzmir / Türkiye
MW Total Power IT Power Project Duration Customer
12 MW 4 MW Ongoing
Project Area White Space Area Role in the Project
6.702 sqm 2.157 sqm Design & Build Turnkey MEP, Data Hall Infrastructure Works
European Data Center 3rd Module Tekirdağ / Türkiye
MW Total Power IT Power Project Duration Customer
13 MW 4,35 MW Ongoing
Project Area White Space Area Role in the Project
7.300 sqm 2.650 sqm Design & Build Turnkey MEP, Data Hall Infrastructure Works
Ankara Data Center 4th Module Ankara / Türkiye
MW Total Power IT Power Project Duration Customer
13 MW 4 MW Ongoing
Project Area White Space Area Role in the Project
5.450 sqm 2.750 sqm Design & Build Turnkey MEP, Data Hall Infrastructure Works
CES 3 Ankara / Türkiye
MW Total Power IT Power Project Duration Customer
2023 - 2025 CES
Project Area White Space Area Role in the Project
38.205,36 sqm
Boreas Technology Production Hub Tekirdağ / Türkiye
MW Total Power IT Power Project Duration Customer
2023 - 2024 Boreas Technology
Project Area White Space Area Role in the Project
35.000 sqm
Hotel Komana İstanbul / Türkiye
MW Total Power IT Power Project Duration Customer
2021 - 2024 Serban
Project Area White Space Area Role in the Project
1.477 sqm
TSK Eğitim Vakfı (TAF Education Foundation) Student Dormitory İstanbul / Türkiye
MW Total Power IT Power Project Duration Customer
2021 - 2023 TSK Eğitim Vakfı
Project Area White Space Area Role in the Project
31.000 sqm
DoubleTree by Hilton Çanakkale Çanakkale / Türkiye
MW Total Power IT Power Project Duration Customer
2021 - 2022 DoubleTree by Hilton Çanakkale
Project Area White Space Area Role in the Project
15.600 sqm
Factory and Administrative Building Ankara / Türkiye
MW Total Power IT Power Project Duration Customer
2016 - 2016 CES
Project Area White Space Area Role in the Project
16.000 sqm
CES Hab Ankara / Türkiye
MW Total Power IT Power Project Duration Customer
CES
Project Area White Space Area Role in the Project
34.882 sqm
Ballistic Test Center Ankara / Türkiye
MW Total Power IT Power Project Duration Customer
2019 - 2019 CES
Project Area White Space Area Role in the Project
22.000 sqm
Public Critical Facilities Türkiye
MW Total Power IT Power Project Duration Customer
Serban
Project Area White Space Area Role in the Project
Data Center Campus Cologne / Germany
MW Total Power IT Power Project Duration Customer
100,0 MW 80,0 MW Ongoing
Project Area Role in the Project Scope
50.000 sqm Tech DD, Test Fit Planning, Preliminary Building Permit, Building Application General Planning
Data Center with Office Building Cologne / Germany
MW Total Power IT Power Project Duration Customer
20,0 MW 16,0 MW Ongoing
Project Area Role in the Project Scope
15.000 sqm Tech DD, Test Fit Planning, Preliminary Building Permit, Building Application General Planning
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
84,0 MW 70,0 MW Ongoing
Project Area Role in the Project Scope
70.000 sqm Execution Planning General Planning
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
24,0 MW 16,0 MW Ongoing
Project Area Role in the Project Scope
15.000 sqm Execution Planning Architectural
Data Center with Office Building Berlin / Germany
MW Total Power IT Power Project Duration Customer
180,0 MW 150,0 MW Ongoing
Project Area Role in the Project Scope
110.000 sqm Tech DD, Test Fit Planning, Building Application (expected) General Planning
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
126,0 MW 105,0 MW Ongoing
Project Area Role in the Project
90.000 sqm Tech DD, Test Fit Planning, Preliminary Building Permit
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
100,0 MW 80,0 MW Ongoing
Project Area Role in the Project Scope
48.000 sqm Construction Management Architectural
Data Center with Office Building Berlin / Germany
MW Total Power IT Power Project Duration Customer
9,6 MW 7,5 MW Ongoing
Project Area Role in the Project Scope
5.500 sqm Tech DD, Test Fit Planning, Preliminary Building Permit General Planning
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
46,0 MW 38,0 MW Ongoing
Project Area Role in the Project Scope
31.000 sqm Tech DD, Test Fit Planning, Preliminary Building Application General Planning
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
14,4 MW 12,0 MW 2017 - 2018
Project Area Role in the Project Scope
11.400 sqm Execution Planning, Tendering, Construction Management Architectural
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
14,4 MW 12,0 MW 2018 - 2019
Project Area Role in the Project Scope
11.225 sqm Execution Planning, Tendering, Construction Management Architectural
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
14,4 MW 12,0 MW 2018 - 2019
Project Area Role in the Project Scope
11.225 sqm Execution Planning, Tendering, Construction Management Architectural
Building Extension and Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
2,4 MW 2,0 MW 2018
Project Area Role in the Project Scope
2.770 sqm Design & Permitting Architectural
Data Center Campus Offenbach a.M. / Germany
MW Total Power IT Power Project Duration Customer
450,0 MW 350,0 MW 2018 - 2019
Project Area Role in the Project Scope
119.300 sqm Design, Permitting & Tendering General Planning
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
45,0 MW 32,0 MW 2018 - 2019
Project Area Role in the Project Scope
32.000 sqm Design & Permitting General Planning
Conversion into a Data Center Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
0,0 MW 0,0 MW 2018 - 2019
Project Area Role in the Project Scope
1.500 sqm Construction Management Architectural
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
20,0 MW 16,0 MW 2017 - 2019
Project Area Role in the Project Scope
20.000 sqm Design, Permitting, Execution Planning & Construction Management General Planning
Building Extension and Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
12,5 MW 10,0 MW 2017 - 2019
Project Area Role in the Project Scope
8.000 sqm Design, Permitting & Execution Planning Architectural
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
18,5 MW 14,0 MW 2017 - 2019
Project Area Role in the Project Scope
15.000 sqm Design, Permitting, Execution Planning & Construction Management Architectural
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
7,8 MW 6,5 MW 2018 - 2019
Project Area Role in the Project Scope
9.600 sqm Design, Permitting, Execution Planning & Construction Management General Planning
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
7,8 MW 6,5 MW 2019 - 2020
Project Area Role in the Project Scope
9.000 sqm Design & Permitting General Planning
Data Center Campus Liederbach i.Ts. / Germany
MW Total Power IT Power Project Duration Customer
120,0 MW 100,0 MW 2021
Project Area Role in the Project Scope
69.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building Sulzbach / Germany
MW Total Power IT Power Project Duration Customer
48,0 MW 24,0 MW 2021 - 2022
Project Area Role in the Project Scope
19.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center Campus Dexheimc / Germany
MW Total Power IT Power Project Duration Customer
800,0 MW 670,0 MW 2021 - 2023
Project Area Role in the Project Scope
600.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building Mainz / Germany
MW Total Power IT Power Project Duration Customer
28,8 MW 24,0 MW 2022
Project Area Role in the Project Scope
9.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
14,4 MW 12,0 MW 2022
Project Area Role in the Project Scope
14.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
100,0 MW 80,0 MW 2023
Project Area Role in the Project Scope
47.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building Offenbach a.M. / Germany
MW Total Power IT Power Project Duration Customer
14,4 MW 12,0 MW 2023
Project Area Role in the Project Scope
13.200 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center Campus Cologne / Germany
MW Total Power IT Power Project Duration Customer
230,0 MW 190,0 MW 2023
Project Area Role in the Project Scope
123.000 sqm Tech DD, Test Fit Planning & Consulting, Audit General Planning
Data Center with Office Building Barcelona / Spain
MW Total Power IT Power Project Duration Customer
20,0 MW 16,8 MW 2023 - 2024
Project Area Role in the Project Scope
15.000 sqm Tech DD, Design, Permitting & Project Management General Planning
Data Center with Office Building Mainz / Germany
MW Total Power IT Power Project Duration Customer
29,0 MW 24,2 MW 2023
Project Area Role in the Project Scope
10.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building Cologne / Germany
MW Total Power IT Power Project Duration Customer
60,0 MW 50,0 MW 2023 - 2024
Project Area Role in the Project Scope
45.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building Cologne / Germany
MW Total Power IT Power Project Duration Customer
60,0 MW 50,0 MW 2023 - 2024
Project Area Role in the Project Scope
40.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building İstanbul / Türkiye
MW Total Power IT Power Project Duration Customer
40,0 MW 32,0 MW 2023
Project Area Role in the Project Scope
30.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building London / United Kingdom
MW Total Power IT Power Project Duration Customer
86,0 MW 72,0 MW 2023 - 2024
Project Area Role in the Project Scope
32.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building London / United Kingdom
MW Total Power IT Power Project Duration Customer
130,0 MW 110,0 MW 2023 - 2024
Project Area Role in the Project Scope
85.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building Milan / Italy
MW Total Power IT Power Project Duration Customer
120,0 MW 100,0 MW 2023
Project Area Role in the Project Scope
45.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building Marseille / France
MW Total Power IT Power Project Duration Customer
60,0 MW 50,0 MW 2024
Project Area Role in the Project Scope
30.000 sqm Tech DD, Test Fit Planning & Consulting General Planning
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
9,6 MW 7,5 MW 2022 - 2024
Project Area Role in the Project Scope
5.000 sqm Tech DD, Test Fit Planning, Preliminary Building Permit Architectural
Data Center with Office Building Cologne / Germany
MW Total Power IT Power Project Duration Customer
9,6 MW 7,5 MW 2023
Project Area Role in the Project Scope
12.000 sqm Tech DD, Test Fit Planning & Consulting Architectural
Data Center with Office Building Leipzig / Germany
MW Total Power IT Power Project Duration Customer
12,0 MW 10,0 MW 2023 - 2024
Project Area Role in the Project
17.000 sqm Tech DD, Test Fit Planning & Consulting
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
9,6 MW 7,5 MW 2023 - 2024
Project Area Role in the Project Scope
11.000 sqm Execution Planning Architectural
10 Edge Data Center with Offices Germany
MW Total Power IT Power Project Duration Customer
7,2 MW 6,0 MW 2022 - 2023
Project Area Role in the Project Scope
7.000 sqm Design & Permitting Process Consulting Architectural
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
54,0 MW 45,0 MW 2024
Project Area Role in the Project Scope
50.000 sqm Tech DD & Consulting General Planning
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
12,0 MW 10,0 MW 2023 - 2024
Project Area Role in the Project Scope
9.000 sqm Tech DD, Test Fit Planning, Preliminary Building Permit General Planning
Data Center with Office Building Norway
MW Total Power IT Power Project Duration Customer
40,0 MW 35,0 MW 2023
Project Area Role in the Project Scope
11.000 sqm Tech DD General Planning
3 Edge Data Center with Offices Denmark
MW Total Power IT Power Project Duration Customer
5,4 MW 4,5 MW 2023
Project Area Role in the Project Scope
1.500 sqm Tech DD General Planning
Data Center with Office Building Neu-Isenburg / Germany
MW Total Power IT Power Project Duration Customer
9,6 MW 7,5 MW 2023 - 2024
Project Area Role in the Project Scope
10.000 sqm Tech DD, Test Fit Planning, Preliminary Building Application Architectural
Data Center with Office Building Frankfurt a.M. / Germany
MW Total Power IT Power Project Duration Customer
12,0 MW 10,0 MW 2023 - 2024
Project Area Role in the Project Scope
9.000 sqm Consulting Architectural
Gebze Data Center Building 2nd Module Construction Project Kocaeli / Türkiye
MW Total Power IT Power Project Duration Customer
10 MW 3 MW 2018 - 2018
Project Area White Space Area Role in the Project
4.250 sqm 2.000 sqm TURNKEY Construction MEP Works
Gebze Data Center Building 3rd Module Construction Project Kocaeli / Türkiye
MW Total Power IT Power Project Duration Customer
10 MW 3 MW 2018 - 2018
Project Area White Space Area Role in the Project
4.250 sqm 2.000 sqm TURNKEY Construction MEP Works
European Data Center Building Tekirdağ / Türkiye
MW Total Power IT Power Project Duration Customer
20 MW 4 MW 2019 - 2020
Project Area White Space Area Role in the Project
43.000 sqm 6.800 sqm TURNKEY Construction MEP, Data Hall Infrastructure Works
Gebze Data Center Building 4th Module Construction Works Project Kocaeli / Türkiye
MW Total Power IT Power Project Duration Customer
13 MW 4 MW 2021 - 2022
Project Area White Space Area Role in the Project
4.250 sqm 2.000 sqm Design & Build Turnkey MEP, Data Hall Infrastructure Works
Gebze Data Center Building 5th Module Construction Works Project Kocaeli / Türkiye
MW Total Power IT Power Project Duration Customer
13 MW 4 MW 2022 - 2023
Project Area White Space Area Role in the Project
4.250 sqm 2.000 sqm Design & Build Turnkey MEP, Data Hall Infrastructure Works
Ankara Data Center 2nd Module Ankara / Türkiye
MW Total Power IT Power Project Duration Customer
13 MW 4 MW 2022 - 2023
Project Area White Space Area Role in the Project
5.450 sqm 2.750 sqm TURNKEY Construction MEP, Data Hall Infrastructure Works
Ankara Data Center 3rd & 7th Modules Ankara / Türkiye
MW Total Power IT Power Project Duration Customer
13 MW 4,9 MW 2023 - 2024
Project Area White Space Area Role in the Project
7.700 sqm 2.840 sqm Design & Build Turnkey MEP, Data Hall Infrastructure Works
European Data Center 2nd Module (in provisional acceptance phase) Tekirdağ / Türkiye
MW Total Power IT Power Project Duration Customer
13 MW 4 MW 2023 - 2024
Project Area White Space Area Role in the Project
6.600 sqm 2.200 sqm Design & Build Turnkey MEP, Data Hall Infrastructure Works